|
|
|
|
Contents
2.1.1
Monitoring Requirements and Equipment
2.1.2
Monitoring Schedule for the Reporting Month
2.1.3
Results and Observations
2.2.1
Monitoring Requirements and Equipment
2.2.2
Monitoring Schedule for the Reporting Month
2.2.3
Results and Observations
2.5.1
Preserved Plant Species of Conservation Importance
2.5.2
Transplanted Plant Species of Conservation Importance
2.7.2
Monitoring Schedule for the Reporting Month
2.7.3
Results and Observations
2.10 LANDSCAPE AND VISUAL MONITORING
2.11 IMPLEMENTATION STATUS OF ENVIRONMENTAL
MITIGATION MEASURES
2.12 SUMMARY
OF COMPLAINTS, NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS
Annex B
Environmental Mitigation Implementation Schedule
Annex C
Status of Submissions and Implementation Status of Mitigation Measures
under EP
Annex D
Status of Statutory Environmental Requiremens
Annex E1
Calibration Certificates for Air Quality
Annex E2
Monitoring Schedule for Air Quality
Annex E3
Monitoring Results for Air Quality
Annex E4
Event and Action Plan for Air Quality
Annex F1
Calibration Certificates for Noise
Annex F2
Monitoring Schedule for Noise
Annex F3
Monitoring Results for Noise
Annex F4
Event and Action Plan for Noise
Annex G
Compensation Woodland Monitoring
Annex H
Preserved/Transplanted Plant Species of Conservation Importance
Monitoring
Annex H1
Preserved Plant Species of Conservation Importance
Annex H2
Transplanted Plant Species of Conservation Importance
Annex I
Eco-shoreline Monitoring
Annex J3
Event and Action Plan
Annex K
Landscape and Visual Monitoring
Annex K1
Examples of Landscape and Visual Mitigation Measures
Annex K2
Event and Action Plan for Landscape and Visual Mitigation Measures
Annex M Monitoring
Schedule for the Next Reporting Period
Acronyms
and ABBREVIATIONS
Acronyms |
Description |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CEDD |
Civil Engineering and Development Department |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EIS |
Ecologically Important Stream |
EM&A |
Environmental Monitoring and Audit |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ER |
Engineer's Representative |
ERM |
ERM-Hong Kong, Limited |
ET |
Environmental Team |
HVS |
High Volume Sampler |
IEC |
Independent Environmental Checker |
PDA |
Planned Development Area |
PME |
Powered Mechanical Equipment |
QPME |
Quality Powered Mechanical Equipment |
RAP |
Remediation Action Plan |
RR |
Remediation Report |
RTTM |
Real Time Tracking and Monitoring |
SS |
Suspended Solid |
TCB |
Tung Chung Bay |
TCE |
Tung Chung East |
TCNTE |
Tung Chung New Town Extension |
TCW |
Tung Chung West |
The Project |
Tung Chung New Town Extension (East) |
THW |
Tai Ho Wan |
TSP |
Total Suspended Particulate |
Updated EM&A Manual |
Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension prepared by ERM under Agreement No. CE 60/2017 (EP) and deposited to EPD under Environmental Permit No. EP-519/2016 |
Tung Chung New Town Extension (TCNTE) is one of the major
initiatives under the Government's multi-pronged approach to increase land
supply to meet Hong Kong's medium- to long-term needs for housing, economic and
social developments. The Environmental Impact Assessment (EIA) Report for
TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the
Environmental Permit (EP) No. EP-519/2016, covering the construction and
operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP
cover both Tung Chung East (TCE) and Tung Chung West (TCW). ERM-Hong
Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team
(ET) for the construction and operation of TCE Project (“the Project”) in
accordance with the requirements specified in the EP, Updated Environmental
Monitoring and Audit (EM&A) Manual, EIA Report of the TCNTE project and
other relevant statutory requirements.
The construction of the Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance
Works (“Contract 1”) at TCE commenced on 9 July 2018.
The construction of the Contract No. NL/2020/02 - Tung Chung
New Town Extension – Salt Water Supply System
(“Contract 2”) at TCE commenced on 4 September 2021.
The construction of the Contract No. NL/2020/03 - Tung Chung
New Town Extension – Major Infrastructure Works in Tung Chung East (“Contract
3”) at TCE commenced on 5 November 2021.
The construction of the Contract No. NL/2020/07 - Tung Chung
New Town Extension – Tai Ho Interchange (“Contract 7”) at TCE commenced on 15
March 2022.
This is the Monthly EM&A report presenting the EM&A
works carried out during the period from 1 to 31 December 2023 for the TCE
Project in accordance with the Updated EM&A Manual.
A summary of monitoring and audit activities conducted in
the reporting period is listed below:
Air Quality
Monitoring
6 sessions
Noise
Monitoring
6 sessions
Preserved Plant
Species Monitoring
1 session
Transplanted
Plant Species Monitoring 1 session
Soft Shore
Ecological Monitoring
1
session
Environmental Site Inspection
·
Contract
1
3 sessions
·
Contract
2
4 sessions
·
Contract
3
5 sessions
·
Contract
7
4 sessions
Environmental Management Meeting
·
Contract
1
1 session
·
Contract
2
1 session
·
Contract
3
1 session
·
Contract
7
1 session
Environmental auditing works, including weekly site
inspections of construction works conducted by the ET, audit of implementation
of Complaint Management Plan, Eco-shoreline Implementation Plan, Detailed
Preservation and/or Translocation of Plant Species of Conservation Importance,
Detailed Compensatory Woodland Planting Plan and Waste Management Plan were conducted in the
reporting period. Based on the audit results and the observation for the
reporting period, environmental pollution control and mitigation measures for
the Project were properly implemented.
No exceedance of Action and Limit Levels was recorded for
construction air quality monitoring in the reporting period.
No exceedance of Action/ Limit Levels was recorded for
construction noise monitoring in the reporting period.
Water quality monitoring was suspended in the reporting
period.
The construction of vertical eco-shoreline, mangrove
eco-shoreline and rocky eco-shoreline has been substantially completed. Monitoring was conducted during the reporting period.
Impact soft shore ecological monitoring at Tung Chung Bay
and Tai Ho Wan has been completed and the post-construction soft shore
ecological monitoring commenced in December 2023.
Based on the post-construction
monitoring conducted during the reporting period, there was no evidence showing
any significant difference in intertidal communities when compared against the
data obtained during baseline monitoring. The ET will continue to observe
the change in density or the distribution pattern of horseshoe crab, seagrass
and intertidal soft shore communities taking into account natural fluctuation in respect of the
occurrence and distribution pattern.
There was no notification of summons or prosecution
recorded in the reporting period.
One (1) environmental complaint related to Contract 1 and
two (2) environmental complaints related to Contract 3 were received in the
reporting period. Investigations were conducted for
the environmental complaints in accordance with the complaint handling process
as stated in the Complaint Management Plan.
There was no reporting change in
the reporting period.
Potential environmental impacts arising from the upcoming
construction activities in the next reporting period of January 2024 are mainly
associated with dust emission, noise from plant operation during normal working
hours and restricted hours, handling and storage of C&D materials generated
from construction activities, efficiency of wastewater and drainage management
and tree protection. The ET will keep track on
the construction works to confirm compliance of environmental requirements and
the proper implementation of all necessary mitigation measures. The ET
will also recommend to the Contractor about the environmental toolbox topics on
the abovementioned key issues for the coming month.
Tung Chung New Town Extension (TCNTE) is one
of the major initiatives under the Government's multi-pronged approach to
increase land supply to meet Hong Kong's medium- to long-term needs for
housing, economic and social developments. The Environmental Impact Assessment
(EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on 8 April
2016 and the Environmental Permit (EP) No. EP-519/2016, covering the
construction and operation of TCNTE, was granted on 9 August 2016. The EIA
Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is commissioned to undertake
the role of Environmental Team (ET) for the construction and operation of TCE
Project (“the Project”) in accordance with the requirements specified in the
EP, Updated Environmental Monitoring and Audit (EM&A) Manual[1], EIA Report of the TCNTE project[2] and other relevant statutory
requirements.
The TCNTE comprises the
following elements:
(a)
TCE Project
1. Reclamation of the seabed by a non-dredged method at
TCE to form a total of about 130 hectares of land;
2. Construction of about 4.9 kilometers
of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three
circulation drains and a seawater intake at TCE;
3. Provision of infrastructure for Tung Chung Area 58,
including construction of a single two-lane road with a footpath and the
associated utility works;
4. Construction of proposed open space;
5. Construction of roads, footpaths, cycle tracks and the
associated junction / road improvement works;
6. Engineering infrastructure works covering drainage,
sewerage, waterworks (including a fresh water service
reservoir, a salt water service reservoir and a salt water pumping station),
common utility tunnels and landscaping works; and
7. Implementation of environmental mitigation measures
and environmental monitoring and audit programme for the works.
(b)
TCW Project
1. Site formation works at TCW;
2. Construction of proposed open space;
3. Construction of the River Park including a
visitor centre at TCW; and
4. Construction of sustainable urban drainage
systems at TCW.
The locations of Contracts 1, 2,
3 and 7 are shown in Figure
1.1 to 1.4. The construction and the reclamation related marine
works of Contract 1 commenced on 9 and 13 July 2018, respectively. The
construction of Contracts 2, 3 and 7 commenced on 4 September 2021, 5 November
2021 and 15 March 2022, respectively.
1.2
SCOPE OF THE EM&A REPORT
This is the Monthly EM&A
Report for the TCE Project which summarises the key
findings of the EM&A programme during the
reporting period from 1 to 31 December 2023 for the construction works.
The organization structure of
the Project is shown in Annex
A. The key personnel contact names and contact details are
summarized in Table 1.1 below.
Table 1.1 Contact
Information of Key Personnel
Position |
Name |
Telephone |
|
Environmental Team (ET) (ERM-Hong Kong, Limited) |
ET Leader |
Kelvin So |
3894 9504 |
Deputy ET Leader
|
Raymond Chow
|
3894 9509
|
|
Independent Environmental Checker (IEC) (Binnies Hong Kong Limited) |
IEC |
Manuel Chua |
3894 9807 |
Deputy IEC
|
Edward Lau |
3894 9695 |
|
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
|||
Civil Engineering and Development Department |
Senior Geotechnical Engineer |
C H Yan |
3894 9702 |
Marine Conservation Officer |
Wo King Tai |
3894 9707 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Chris Cheung |
3894 9604 |
|
Senior Resident Engineer |
Chris Chow |
3894 9651 |
|
Resident Engineer |
Victor Chan |
3894 9666 |
|
Senior Inspector of Works |
C K Liu |
3894 9733 |
|
Contractor (Build King – SCT Joint Venture)
|
Site Agent |
David Wong |
9653 8635 |
Civil Division Head |
Marco Chan |
9257 7033 |
|
Environmental Officer |
Issac Wong |
9873 8968 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Patrick C Y Yeung |
2231 4435 |
Electrical & Mechanical Engineer |
Samson K L Yip |
2231 4460 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Sunny Ng |
3894 9605 |
|
Senior Resident Engineer |
Vincent Leung |
3894 9645 |
|
Resident Engineer |
Amen Fung |
3894 9676 |
|
Senior Inspector of Works |
Wong Ting Yu |
3894 9706 |
|
Contractor (China Geo-Engineering Corporation)
|
Construction Manager |
Ambrose Kwong |
6198 7787 |
Site Agent |
Timothy Lo |
9661 2662 |
|
Construction Team Leader |
Aaren Li |
6468 8138 |
|
Environmental Officer |
Peter Ho |
9457 0120 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
|||
Civil Engineering and Development Department
|
Senior Engineer |
Eddie W C Lam |
2231 4445 |
Senior Engineer |
Phoebe Tang |
2231 4423 |
|
Engineer |
Timothy H M Chan |
2231 4473 |
|
Engineer |
Colin K C Wong |
2231 4417 |
|
Engineer |
Wing Chen |
3894 9704 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Gloria Tang |
3894 9639 |
|
Senior Resident Engineer |
Winston Wong |
3894 9650 |
|
Resident Engineer |
David Li |
3894 9684 |
|
Resident Engineer |
Alvis Li |
3894 9558 |
|
Resident Engineer |
Anson Yip |
3894 9559 |
|
Senior Inspector of Works |
Douglas Ng |
3894 9737 |
|
Contractor (Build King Civil Engineering Limited)
|
Construction Manager |
Cheung Siu Lun |
2272 3680 |
Site Agent |
Paul Lui |
9095 7922 |
|
Deputy Site Agent |
Aldous Lo |
9225 0368 |
|
Construction Team Leader |
Ken Yau |
9197 2219 |
|
Environmental Officer |
Allen Wong |
6012 2643 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Phoebe Tang |
2231 4423 |
Engineer |
S H Leung |
2231 4449 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Kelvin Kwan |
3894 9641 |
|
Senior Resident Engineer |
Brian Li |
3894 9556 |
|
Resident Engineer |
Kingsley Ho |
3894 9552 |
|
Resident Engineer |
Carl Yu |
3894 9671 |
|
Senior Inspector of Works |
Douglas Ng |
3894 9554 |
|
Contractor (Build King Civil Engineering Limited) |
Site Agent |
Hon Yee |
9090 3109 |
Deputy Site Agent |
Vincent Kwan |
9833 1313 |
|
Construction Team Leader |
Vincent Lo |
9883 9229 |
|
Environmental Officer |
Nash Wong |
9810 1946 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
As informed by the Contractor,
details of the major works carried out in this reporting period are listed
below:
Table 1.2 Major Activities in
the Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
· Placing of sorted public fill · Box culvert construction |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of service reservoir, deflector wall and rigid barrier at Portion 3 · CLP cable duct laying works at Wong Lung Hang at Portion 3 · Watermain laying works at Portion 3 along Chung Yan Road, Man Tung Road, Yi Tung Road and inside WSD facilities · Pipe jacking works at Portion 3 · Road widening and watermain laying works at Yi Tung Road at Portion 4 · Installation of ELS and Pipe laying for drainage works at Portion 5A |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation works for noise barrier at Portion 11 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation and pipe laying for rising main and watermain at Portion 146-5 to 146-14 · Pile cap excavation and RC for Pak Mong bridge at 146-3 · Trench excavation, pipe piles and pipe laying works at Portions 32 (Sham Shui Kok Drive), Portion 34 Phase 2, and Portions 38 · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Trench excavation at Portion 33 · Sheetpiling works at Portion 33 Jacking pit · Pipe piles at Portion 32 for Receiving pit · Trench excavation at Portion 38 · RC and ELS or construction of retaining walls FR1 · RC works for Pak Mong Subway Extension Phase 1 · Temporary working platform at abutment A1a ,A2b · RC works for RW-R2, RW-R3 and ELS for RW-RW4 at Portion 146-2 and 146-6 · ELS at RW-R7 · Mini-piles at Wall E · Pipe Piles for Casting Yard A2 · Bored Piles at Bridge A2b · Site clearance and tidiness |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The environmental mitigation
implementation schedule is presented in Annex B.
The status for all environmental
aspects is presented in Table 1.3. The EM&A requirements
remained unchanged during the reporting period.
Table 1.3 Summary of Status for the Environmental Aspects
under the Updated EM&A Manual
Parameters |
Status |
|
Air Quality |
||
Baseline Monitoring |
The results of baseline air quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times every six days |
|
Noise |
|
|
Baseline Monitoring |
The results of baseline noise monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted once per week |
|
Impact Monitoring for Road Traffic Noise during Operational Phase |
To be conducted during operational phase |
|
Fixed Noise Commissioning Test |
To be implemented by the Contractor before operation of TCNTE |
|
Water Quality |
|
|
Baseline Monitoring |
The results of baseline water quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
Suspended for TCE with approval from EPD |
|
Waste Management |
|
|
Waste Monitoring |
On-going |
|
Land Contamination |
|
|
Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR) |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Ecology |
|
|
Monitoring for Compensation Woodland
|
Compensation Woodland Planting was completed on 30 September 2022 On-going, monitoring conducted quarterly |
|
Monitoring for Emergent Plant inside the future River Park |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Translocated Amphibians of Conservation Importance |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Preserved/Transplanted Plant Species of Conservation Importance
|
On-going, for preserved plant species, monitoring conducted once per month; for transplanted plant species, replacement planting was carried out on 28 April 2023 and 19 September 2023, and monitoring conducted once per month for the first year |
|
Monitoring for Tung Chung Stream EIS and Wong Lung Hang EIS
|
To be conducted under TCW. Refer to the EM&A Reports of TCW. Monitoring for Wong Lung Hang was not required and the proposal was accepted by EPD on 2 September 2021 |
|
Eco-shoreline Monitoring |
Dry season monitoring was conducted |
|
Tung Chung Bay and Tai Ho Wan Baseline Monitoring |
The results of baseline soft shore ecological monitoring at Tung Chung
Bay and Tai Ho Wan were reported in Baseline Monitoring Report and submitted
to EPD under EP Condition 3.4 |
|
Tung Chung Bay and Tai Ho Wan Impact Monitoring |
Completed |
|
Tung Chung Bay and Tai Ho Wan Post-construction
Monitoring |
On-going for TCE, monitoring conducted quarterly |
|
Landscape and Visual |
|
|
Baseline Monitoring |
The results of baseline landscape and visual monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going |
|
Site Environmental Audit |
|
|
Regular Site Inspection |
On-going |
|
Dolphin Watching Plan implementation measures |
Completed |
|
Works Vessel Travel Route Plan implementation measures |
Completed |
|
Silt Curtain Deployment Plan implementation measures |
All silt curtain was removed in accordance with the Silt Curtain Deployment Plan and after obtaining the acceptance from EPD |
|
Spill Response Plan implementation measures |
Completed |
|
Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Detailed Compensatory Woodland Planting Plan implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Waste Management Plan implementation measures |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Complaint Hotline and Email Channel |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Environmental Log Book |
On-going |
|
Taking into account the
construction works, impact monitoring of air quality, noise, soft shore ecological monitoring and waste
management were carried out in the reporting period. The monitoring
schedule of air quality, noise and soft shore ecological monitoring are
provided in Annex E2, Annex F2 and Annex J1
respectively.
The EM&A programme also
involved environmental site inspections and related auditing conducted by the
ET for checking the implementation of the required environmental mitigation
measures recommended in the approved EIA Report and relevant EP submissions,
including Complaint Management Plan, Eco-shoreline Implementation Plan, Detailed
Preservation and/or Translocation Plan for Plant Species of Conservation
Importance, Detailed Compensatory Woodland Planting Plan and Waste Management
Plan.
To promote the environmental awareness and enhance the
environmental performance of the contractors, environmental trainings and
regular environmental management meetings were conducted during the reporting
period, which are summarized as below:
Four (4) environmental management committee meetings were held
with the Contractors of Contract 1, 2, 3 and 7 and ER, ET, IEC and CEDD on 21,
20, and 12 December 2023, respectively;
Environmental toolbox trainings on dust suppression, nuisance
to residence (light pollution/ sudden noise/ dusty work), site hygiene
(rubbish/ mosquito/ rodent control), suspension of work (pollution), wastewater
handling, discharge and treatment facilities, construction noise permit,
chemical handling, use of spill kits, waste management and disposal on 1, 6, 8,
13, 15, 20, 22, 27, 29 December 2023 were conducted for Contract 1;
Environmental toolbox trainings on excavation, rock bolts, rock
dowels, soil nailing on 7 and 18 December 2023 were conducted for Contract 2;
Environmental toolbox trainings on construction dust and suppression, construction noise and suppression, wastewater handling, discharge and treatment facilities, waste collection, handling and disposal, handling and storage of chemical spillage, site plant and machinery (operation and maintenance) on 4, 7, 12, 14, 19, 21,28 December 2023 were conducted for Contract 3;
Environmental toolbox trainings on
formwork and falsework, building demolition, fencing, excavation on 6, 13, 20
and 27 December 2023 were conducted for Contract 7.
The status of statutory
environmental compliance with the EP conditions under the EIAO, submission
status under the EP and implementation status of mitigation measures are
presented in Annex C.
The environmental licenses and
permits, including environmental permit, discharge license under Water
Pollution Control Ordinance, registration as chemical waste producer,
construction noise permit and specified processes license, which were valid in
the reporting period are presented in Annex D. No non-compliance with environmental
statutory requirements was recorded.
The EM&A programme
for the Project required environmental monitoring for air quality, noise, water
quality and marine ecology as well as environmental site inspections for air
quality, noise, water quality, waste management, marine ecology and landscape
and visual impacts. The EM&A requirements and related findings for
each component are summarized in the following sections.
According to the Updated
EM&A Manual of the Project, impact air quality monitoring in terms of
1-hour Total Suspended Particulate (TSP) was conducted three (3) times every
six (6) days when the highest dust impact was expected. The Action and Limit
Levels of the air quality monitoring is provided in Table 2.1 below.
Table 2.1 Action and Limit
Levels for 1-hour TSP
Location |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Monitoring station for Tung Chung East |
279 |
500 |
Portable direct reading dust meters were used to measure
1-hour TSP levels in undertaking the air quality monitoring for the
Project. The proposed use of portable direct reading dust meters was
submitted to IEC and obtained agreement from the IEC as stated in Section 5.5
of the Updated EM&A Manual. With the use of direct reading dust
meter, it can allow prompt and direct results for the EM&A reporting and
the implementation of the event and action plan. The portable direct reading
dust meter would be calibrated every year against High Volume Sampler (HVS) to
check the validity and accuracy of the results measured by direct reading
method.
The monitoring location and equipment used in the impact air
quality monitoring programme are summarized in Table
2.2 and illustrated in Figure
2.1. Copies of the calibration certificates for the equipment are
presented in Annex E1,
which showed that the portable direct reading dust meter is capable of
providing comparable results with that provided by a
HVS.
Table 2.2 Air Quality
Monitoring Details
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
DM-1 |
Tung Chung Area 56 – Ying Tung Estate |
1-hour TSP |
Three times per six days during the construction period of the Project |
1, 7, 13, 19, 23 and 29 December 2023 |
1-hour TSP Dust Meter SIBATA LD-3B (S/N: 627784) |
Note:
It should be noted that impact monitoring at other construction dust monitoring
locations at TCE as stated in the Updated EM&A Manual will commence after
the flat intake (for Monitoring Stations DM-2, DM-3
and DM-4).
The schedule for air quality
monitoring during the reporting period is provided in Annex E2.
The monitoring results for 1-hour TSP are summarized in Table 2.3. The
monitoring data and the graphical presentation are provided in Annex E3.
Table 2.3 Summary of 1-hour
TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
52 |
40-63 |
279 |
500 |
Major dust sources in the reporting period included haul
road traffic and excavation under the Project.
No exceedance of Action and Limit
Levels was recorded for construction air quality monitoring in the reporting
period. No action was thus required to be undertaken in accordance with
the Event and Action Plan presented in Annex
E4.
According to the Updated
EM&A Manual of the Project, impact noise monitoring was conducted once per
week during the construction phase of the Project. The Action and Limit
Level for construction noise of the Project is provided in Table 2.4
below.
Table 2.4 Action and Limit
Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) a, b |
Note:
a Limit
level is exceeded when Leq ≥ 75 dB(A). If
works are to be carried out during restricted hours, the conditions stipulated
in the construction noise permit issued by the Noise Control Authority have to be followed.
b Reduce to 70 dB (A) for schools and 65 dB (A) during school examination
periods.
Noise monitoring was performed using sound level meter at
the designated monitoring stations NMS-CA-1A [3] [4] and NMS-CA-4 (Figure 2.2; Table 2.5) in
accordance with the requirements stipulated in the Updated
EM&A Manual. Acoustic calibrator was
deployed to check the sound level meters at a known sound pressure level.
Details of the deployed equipment are provided in Table 2.5.
Copies of the calibration certificates for the equipment are presented in Annex F1.
Table 2.5 Noise Monitoring
Details
Monitoring Station a |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
NMS-CA-1A b |
Residential premise in Tung Chung East – Century Link/Ying Hong Road c |
30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded. |
Once per week for 30 mins during the construction period of the Project |
1, 7, 13, 19, 23 and 29 December 2023 |
Sound Level Meter: Rion NL-52 (S/N: 00331805)
Acoustic Calibrator: LARSON DAVIS CAL200 (S/N: 10227) |
NMS-CA-4 |
Residential premise in the reclamation area next to Tung Chung East – Ying Tung Estate |
Note:
a It should be noted that impact monitoring at
other construction noise monitoring locations at TCE as stated in the Updated
EM&A Manual will commence after the flat intake of residential premise in
TCE (for Monitoring Station NMS-CA-1) and operation of schools (for Monitoring
Stations NMS-CA-2 and NMS-CA-3).
b Impact
monitoring at monitoring station NMS-CA-1A commenced on 19 September 2018 in
view of the close vicinity of the construction works near the residential area
at Century Link.
c Due to
land handover issue, NMS-CA-1A was relocated to Ying Hong Road which is located
60m away from the original location. Proposal on the relocation of
NMS-CA-1A was approved by IEC on 23 November 2018. Noise monitoring at
the relocated location commenced since 24 November 2018.
The schedule for noise
monitoring during the reporting period is provided in Annex F2.
Results for noise monitoring are
summarized in Table 2.6. The monitoring data and the graphical
presentation are provided in Annex
F3.
Table 2.6 Summary of
Construction Noise Monitoring Results in the Reporting Period
Monitoring Station |
Average, dB(A), |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
NMS-CA-1A |
67.9 |
66.2-69.2 |
75 |
NMS-CA-4 |
68.4 |
67.0-70.0 |
75 |
Major noise sources during the noise monitoring included
noise from plant operation, craning, piling, haul road traffic, nearby traffic and aircraft as well as nearby construction
sites.
No Action/ Limit Level exceedance was recorded for
construction noise monitoring in the reporting period. Investigation was
conducted for the complaint in accordance with the Event and Action Plan (Annex F4) and the details
are provided in Section 2.13.
No monitoring event for impact
water quality monitoring was conducted at all designated monitoring
stations during the reporting period. Water quality monitoring has been
suspended since 3 October 2023 as all reclamation works and marine construction
activities have been completed.
Compensation woodland planting under Contract 2 was
completed on 30 September 2022. With the approval from EPD on the
monitoring proposal in August 2023, the monitoring for compensation woodland
was commenced in September 2023. Quarterly post-planting monitoring for
the compensation woodland was carried out on 4, 7, 12, 15 and 27 December 2023.
Photographic record of the compensation woodland planting is provided in Annex G.
Plant species of conservation importance, including three
individuals of Aquilaria sinensis and 33 individuals of Gmelina
chinensis, were identified within works areas for Contract 2 during the
survey conducted in August 2021. All individuals of Aquilaria sinensis
and 31 individuals of Gmelina chinensis were
recommended being preserved in-situ while two individuals of Gmelina
chinensis (RT-07 and RT-08) were recommended being transplanted to the
receptor site in accordance with the Detailed Preservation and/or Translocation
Plan for Plant Species of Conservation Importance approved under Condition 2.21
of EP-519/2016.
Initial tree survey was conducted in September 2021 under
Contract No. NL/2020/02 before the commencement of construction works.
According to the initial tree survey conducted, the in-situ preserved
plant species of conservation importance of which one individual of Aquilaria
sinensis and six individuals of Gmelina chinensis were found
missing.
During the monthly monitoring of
the in-situ preserved plant species of conservation importance in
November 2023, one individual of Aquilaria sinensis and one individual
of Enkianthus quinqueflorus
were newly observed and recommended being preserved in-situ.
Registration and measurement for two additional trees were conducted on 4
December 2023.
Monthly monitoring of the in-situ
preserved plant species of conservation importance by the Qualified
Personnel (QP) appointed under Contract 2 was implemented in the reporting
period. Health condition was considered fair for the
majority of the in-situ preserved plant species of conservation
importance, of which two individuals of Gmelina chinensis could not be
monitored as a result of unsafe access to the locations, as recorded during the
monitoring carried out on 29 December 2023.
Tree protection zones for the in-situ preserved plant
species of conservation importance were demarcated. No injuries and/or
damages to the individuals of the in-situ preserved plant species of
conservation importance were reported by the QP since the previous monitoring
events. Photographic record and tree schedule of the preserved plant
species of conservation importance monitoring are provided in Annex H1.
The ET will continue to monitor
the implementation of monitoring of in-situ preserved plant species of
conservation importance.
Site visit to the receptor site for the transplanted plant
species of conservation importance under Contract 2 was carried out on 20
January 2022 prior to the commencement of transplantation works for the
transplanted plant species of conservation importance on 21 January 2022.
The transplanted plant species of conservation importance
were both certified as dead trees by the QP on 15 June 2022 as no living signs
were observed. Replacement planting of new trees of the same species, or
other species to the satisfaction of the Project Manager, at the Contractors’
expense would be deemed necessary in accordance with the conditions under the
approved Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance. Replacement planting of three (3) Aquilaria
sinensis were completed on 28 April 2023.
Monitoring of the replacement planting of Aquilaria
sinensis was carried out on 18 December 2023. Three (3) individuals
of the replacement planting trees were in fair health condition.
Photographic record and tree schedule of Aquilaria sinensis monitoring are
provided in Annex H2.
The transplanted plant species of conservation importance
were watered twice a week to keep the soil moist except in
days with heavy rainfall. The ET will continue to monitor the
implementation of monitoring of in-situ preserved/ transplanted plant species
of conservation importance.
The construction of vertical eco-shoreline, mangrove
eco-shoreline and rocky eco-shoreline has been substantially completed.
Photographic record is provided in Annex I.
Monitoring of different types of
eco-shorelines was on 5, 6 and 19 December 2023. Monitoring shall be
conducted for at least 3 years after the completion of eco-shoreline, twice in
wet season and twice in dry season, in order to
determine the effectiveness of the eco-shoreline in accordance with the Updated
EM&A Manual and Eco-shoreline Implementation Plan.
According to the Updated EM&A Manual of the Project,
post-construction soft shore ecological monitoring has to
be conducted quarterly at each survey location at Tung Chung Bay (TCB) and Tai
Ho Wan (THW) covering wet and dry seasons during the marine construction of the
Project. The soft shore ecological monitoring consisted of qualitative
walk-through surveys, quantitative transect surveys and sedimentation rate
monitoring at the accessible survey locations of TCB and THW.
For qualitative walk-through surveys, the accessible
shoreline of TCB and THW at each of the three shore heights: 2 m, 1.5 m and 1 m
above Chart Datum was surveyed, and organisms encountered were recorded and
their relative abundance noted. In particular, active
search of horseshoe crabs and seagrasses were conducted to confirm whether
these species are present along the sites.
For quantitative transect survey, one 50 – 100 m horizontal
(belt) transect (actual length subject to the site conditions) was surveyed at
each of the three shore heights: 2 m, 1.5 m and 1 m
above Chart Datum of each survey location. On each transect, five
quadrats (50 cm x 50 cm) were placed randomly in each transect to assess the
abundance and distribution of flora and fauna. For each quadrat, surface
layer to 5 cm depth was sieved and microbenthic organisms (e.g. crustaceans)
were recorded and identified. Density of organisms was expressed as
individuals / m2. Areas with seagrass were also recorded and
identified and other information, such as the percentage cover, were also recorded. Sessile animals such as barnacles
and oysters in each quadrat were not counted but estimated as percentage cover
on the rock surface. All species of algae (encrusting, foliose and
filamentous) were also identified and recorded by estimating the percentage
cover on the rock surface. All organisms were identified to the lowest
possible taxonomic level (at least Genus level).
Species encountered outside the quadrat but in the vicinity of survey transect
were also recorded.
For sedimentation rate monitoring, to avoid disturbance to
the mudflat and nuisance to navigation, no fixed marker/monitoring rod was
installed at the monitoring stations. A high precision Global Navigation
Satellite System (GNSS) real time location fixing system was used to locate the
station in the precision of 1 mm, which is reasonable under flat mudflat
topography with uneven mudflat surface only at micro level.
Measurements were taken directly on the mudflat
surface. The Real Time Kinematic GNSS (RTK GNSS) surveying technology was
used to measure mudflat surface levels and 3D coordinates of a survey
point. The RTK GNSS survey was calibrated against a reference station in
the field before and after each survey. The reference station is a survey
control point established by the Lands Department of the HKSAR Government using
professional surveying instruments such as total station, level
and geodetic global navigation satellite system. The coordinates system
is in HK1980 GRID system. The reference station was surveyed and
established by traditional land surveying methods using professional surveying
instruments such as total station, level and geodetic GNSS. The accuracy
was down to mm level and higher than the proposed RTK GNSS cm level so that the
reference control station has relatively higher accuracy. As the
reference control station has higher accuracy, it was set as true evaluation
relative to the RTK GNSS measurement. All position and height correction
were adjusted and corrected to the reference control station.
The precision of the measured mudflat surface level reading
(vertical precision setting) was within 10 mm (standard deviation) after
averaging the valid survey records of the XYZ HK1980 GRID coordinates.
Each survey record at each station was computed by averaging at least three
measurements that are within the above specified precision setting. Both
digital data logging and written records were collected in the field.
Field data on station fixing and mudflat surface measurement were recorded.
The schedule for soft shore ecological monitoring during the
reporting period is provided in Annex J1.
Post-construction soft shore ecological monitoring was
conducted at three (3) monitoring locations at Tung Chung Bay (TCB), situated
in the eastern side (TCB1), southern side (TCB2) and western side (TCB3) as
well as one (1) monitoring location at Tai Ho Wan (THW) as shown in Figure 2.3 during the
reporting period. Representative photographs taken during the impact
monitoring are presented in Figure
2.4.
For qualitative walk-through
surveys, horseshoe crabs and intertidal soft shore communities were recorded
during the impact monitoring. The survey results for each monitoring
location are summarized in Table 2.7 below and detailed in Annex J2.
Table 2.7 Summary of
Qualitative Walk-through Surveys
Location |
Date and Time a |
Horseshoe Crabs |
Seagrass |
No. of Other Intertidal Species |
||
No. of Species |
No. of Individuals |
No. of Species |
Area Coverage (m2) |
|||
TCB2 |
01/12/2023 08:30-12:30 |
1 |
3 |
- |
- |
24 |
TCB3 |
01/12/2023 08:30-12:30 |
1 |
18 |
1 |
236.3 |
31 |
THW |
18/12/2023 09:30-13:30 |
1 |
2 |
- |
- |
23 |
TCB1 |
19/12/2023 09:30-13:00 |
- |
- |
- |
- |
28 |
Note:
a
Quantitative and qualitative transect surveys were conducted on 1 December 2023
at TCB2 and TCB3, 18 December 2023 at THW and 19 December 2023 at TCB1.
For the quantitative transect
surveys, a total of 6,627 individuals were recorded from all transects at
monitoring stations TCB1, TCB2, TCB3 and THW. The most abundant group of
intertidal soft shore communities recorded was gastropods, with a total of
6,492 individuals (relative abundance of 98.0% and density of 432.8 individual
m-2). The summary of the top three dominant species at each
shore height of each monitoring station and the complete list of species and
density recorded are presented in Annex J2. When compared with the results obtained
during the baseline monitoring as presented in the Baseline Monitoring Report [5], there was no indication of a change in
the composition of intertidal communities recorded during the reporting period.
The mudflat surface levels at
the four selected monitoring stations in December 2023 and the corresponding
XYZ HK1980 GRID coordinates are presented in Table 2.8. When
compared with the results obtained during the baseline monitoring as presented
in the Baseline Monitoring Report, slight changes with <0.05 mPD of sediment levels are recorded for the monitoring
stations. The ET will continue to observe the trend of change in sediment
levels over time for further comparison and review.
Table 2.8 Results of
Sedimentation Rate Monitoring
Monitoring Station |
Northing (m) |
Easting (m) |
Z level at December 2023 (mPD) |
Remarks |
TCB1 |
816068.671 |
811129.272 |
1.296 |
Soft mudflat |
TCB2 |
815812.768 |
810917.373 |
1.109 |
Soft mudflat |
TCB3 |
816027.394 |
810696.230 |
1.065 |
Soft mudflat |
THW |
817472.017 |
815850.350 |
1.031 |
Soft mudflat |
Based on the post-construction
monitoring results, there was no evidence showing any significant difference in
intertidal communities when compared against the data obtained during baseline
monitoring. No action is thus required to be undertaken in accordance
with the Event and Action Plan presented in Annex J3. The ET will continue to observe the
change in density or the distribution pattern of horseshoe crab, seagrass and
intertidal soft shore communities taking into account
natural fluctuation in respect of the occurrence and distribution pattern.
Site inspections were carried out on a weekly basis with the
Contractor and ER to monitor the implementation of proper environmental
pollution control and mitigation measures for air quality, noise, water
quality, waste management, marine ecology, landscape and visual impacts and
preservation and/or transplantation of plant species of conservation importance
under the Project. In the reporting period, three (3) site inspections
were carried out on 14, 21 and 28 December 2023 for Contract 1, four (4) site inspections
were carried out on 6, 13, 20 and 27 December 2023 for Contract 2, five (5)
site inspections were carried out on 1, 6, 15, 20 and 29 December 2023 for
Contract 3 and four (4) site inspections were carried out on 5, 12, 19 and 28
December 2023 for Contract 7.
Key observations during the site
inspections are summarized in Table 2.9.
Table 2.9 Key Observations
Identified during the Site Inspection in this Reporting Month
Contract No. |
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
Contract 1 |
14 December 2023 |
Interim Open Rectangular Channel (IORC) • No deficiency was observed. |
• Nil.
|
21 December 2023 |
IORC • Non-Road Mobile Machinery (NRMM) label was not observed on excavator. |
IORC • The Contractor was reminded to affix appropriate NRMM label in accordance with the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation. |
|
28 December 2023 |
IORC • No deficiency was observed. |
• Nil.
|
|
Contract 2 |
6 December 2023 |
Portion 3 • Stockpile was observed not covered.
• General refuse was observed on ground. |
Portion 3 • The Contractor was reminded to cover stockpile properly with impervious sheeting. • The Contractor was reminded to maintain good housekeeping. |
13 December 2023 |
Portion 3 • Oil leakage from excavator hammer was observed. |
Portion 3 • The Contractor was reminded to provide measures to avoid oil leakage from hammer, as such wrapping with impervious sheets. |
|
20 December 2023 |
Portion 6 • Chemical containers were observed placing on the ground. |
Portion 6 • Contractor was reminded to provide a drip tray for chemicals. |
|
27 December 2023 |
Portion 5, 6 • No deficiency was observed |
• Nil. |
|
Contract 3 |
1 December 2023 |
TTA • Chemical was observed placing on ground.
• General refuse was observed on ground. |
TTA • The Contractor was reminded to provide drip tray for chemicals to prevent spillage. • The Contractor was reminded to remove waste and maintain good housekeeping. |
6 December 2023 |
TTA • No deficiency was observed |
• Nil.
|
|
15 December 2023 |
Portion 16a, 16b, 104, TTA • No deficiency was observed |
• Nil. |
|
20 December 2023 |
Portion 104 • Discolored Non-road Mobile Machinery (NRMM) labels were observed on generator and excavator.
Portion 16b • Exposed soil was observed.
TTA • Oil stain was observed on ground. |
Portion 104 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation. Portion 16b • The Contractor was reminded to cover the soil with impervious sheets properly. TTA • The Contractor was urged to remove the oil stains. |
|
29 December2023 |
TTA • Oil stain was observed on ground. • Chemical was observed placing on the ground. |
TTA • The Contractor was urged to remove the oil stains. • The Contractor was reminded to provide drip tray for chemical. |
|
Contract 7 |
5 December 2023 |
Portion 30, 31 • No deficiency was observed. |
• Nil.
|
12 December 2023 |
Portion 30 • Oil leakage from excavator hammer was observed. |
Portion 30 • The Contractor was reminded to provide measures to avoid oil leakage from hammer, as such wrapping with impervious sheets. |
|
19 December 2023 |
Portion 32 • Chemical container was observed placing on the ground. • Accumulated waste was observed. |
Portion 32 • The Contractor was reminded to provide drip tray for chemicals.
• The Contractor was reminded to remove waste in a timely manner. |
|
28 December 2023 |
Portion 146 • Chemical container was observed placing on the ground. |
Portion 146 • The Contractor was reminded to provide drip tray for chemicals. |
The Contractors have rectified all of
the observations identified during environmental site inspections in the
reporting period. The Contractors were reminded
to implement all relevant mitigation measures related to construction
dust, construction noise, water quality and waste management outlined in the
EIA Report and Updated EM&A Manual.
The Contractors of Contract 1, 2, 3 and 7 have registered as
chemical waste producer. Sufficient numbers of
receptacles were available for general refuse collection and sorting.
All dump trucks engaged on site was
equipped with RTTM system during the reporting period. The Surveillance
Team of the ET conducted regular site inspection on the dump trucks and their
track records. No illegal dumping and landfilling of C&D materials
was found during the reporting period.
Wastes generated during this
reporting period include mainly non-inert construction wastes. Reference
has been made to the waste flow tables prepared by the Contractors. The
quantities of different types of wastes and imported
fill materials are summarised in Table 2.10.
Table 2.10 Quantities of Different Waste Generated and
Imported Fill Materials
Contract No. |
Month/ Year |
Inert C&D Materials a (m3) |
Imported Fill b (sand) (m3) |
Imported Fill c (public fill) (m3) |
Inert Construction Waste Re-used d (m3) |
Non-inert Construction Waste e (m3) |
Recyclable Materials f (kg) |
Chemical Wastes (kg) |
TCNTE (East) |
1 to 31 Oct 23 |
0.0 |
0.0 |
0.0 |
153.8 |
633.9 |
0.0 |
0.0 |
1 to 30 Nov 23 |
0.0 |
0.0 |
0.0 |
1,855.6 |
161.3 |
0.0 |
3,000.0 |
|
1 to 31 Dec 23 |
31.8 |
0.0 |
0.0 |
298.9 |
246.2 |
0.0 |
0.0 |
Note:
a Inert construction wastes include
hard rock and large broken concrete, and materials disposed as public fill.
b Imported materials include of sand fill from
any source outside of TCNTE.
c Imported
sorted public fill include all G200, G400 and glass gullet (local recycling
materials) from any source outside of TCNTE.
d Reuse of
inert construction waste generated under the TCNTE contracts.
e Non-inert construction wastes include general refuse
disposed at landfill.
f Recyclable
materials include metals, paper, cardboard, plastics
and others.
Implementation of applicable landscape and visual mitigation
measures was monitored in accordance with the Updated EM&A Manual.
All measures undertaken by the Contractor during the construction phase and
establishment work phase shall be audited by ET to ensure compliance with the
intended aims of the measures.
The implementation status of the environmental protection
measures is summarized below in Table 2.11. Examples of landscape
and visual mitigation measures are presented in Annex K1. The
monitoring programme for detailed design,
construction and establishment stages is presented in Table 2.12.
Event and Action Plan for Landscape and Visual impacts is stated in Annex K2.
Table 2.11 Implementation Status of Landscape and Visual
Mitigation Measures
Landscape and Visual Mitigation Measures during Construction |
Implementation Status |
Relevant Contract(s) in the Reporting Period |
MM1 – Optimization of Construction Areas & Providing Temporary Landscape on Temporary Construction |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA
|
MM2 – Minimize Topographical Changes |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA |
MM3 – Preservation of Potentially Registerable OVTs, Rare and Protective Vegetation |
Tree Protection Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The Contractors’ performance on the implementation of the tree maintenance and protection measures were observed and checked by the ET weekly during construction period. |
All works contracts |
MM4 – Transplanting of Existing Trees
|
Tree Transplanting Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project where trees would unavoidably be affected by the construction works. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The transplanted plant species of conservation importance were both certified as dead trees by the QP on 15 June 2022 as no living signs were observed. |
Contract 2 |
MM5 – Screen Hoarding
|
All works contracts |
|
MM6 – Adopting Non-dredge Method for the Reclamation |
Not applicable during the reporting period. |
NA |
MM9 – Providing Natural Rock Material/ Planting for Artificial Seawall |
Rock armour reused and construction of eco-shoreline (mangrove eco-shoreline, rocky eco-shoreline and vertical eco-shoreline) in progress. The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 1 |
MM10 – Compensatory Planting |
Not applicable during the reporting period. |
NA |
MM11 – Woodland Restoration |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 2 |
MM12 – Screen Planting |
Not applicable during the reporting period. |
NA |
MM13 – Roadside Planting |
Not applicable during the reporting period. |
NA |
MM14 – Aesthetic Design of Built Development |
Not applicable during the reporting period. |
NA |
MM15 – Maximise Greening on Structures |
Not applicable during the reporting period. |
NA |
MM16 – Noise Barrier Design |
Not applicable during the reporting period. |
NA |
MM18 – Landscaping on Slopes |
Not applicable during the reporting period. |
NA |
MM20 – Lighting Control |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
All works contracts |
Table 2.12 Monitoring Programme for Landscape and Visual
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works against the recommendations of the landscape and visual impact assessments within the EIA should be undertaken by the Engineer and Landscape Architect, to ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including design changes on site should also be checked |
Report by CEDD / ER confirming that the design conforms to requirements of EP. |
Approval by Project Proponent |
At completion of design stage |
Construction |
Monitoring of the contractor’s operations during the construction period. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Monthly |
Establishment Works |
Monitoring of the planting works during the 24-months Establishment Period after completion of the construction works. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Bi-monthly |
A summary of the Environmental
Mitigation Implementation Schedule is presented in Annex B. The necessary
mitigation measures were implemented properly for the Project.
There was no notification of summons or prosecution recorded
in the reporting period.
One (1) environmental complaint
related to Contract 1 and two (2) environmental complaints related to Contract
3. Investigations were conducted for the
environmental complaints in accordance with the complaint handling process as
stated in the Complaint Management Plan. Environmental complaints in the
reporting period are summarized below.
|
Complaint(s) |
Investigation/Follow up action(s) |
1
|
Environmental complaint related to Contract 1 regarding dust on 24 November 2023 was referred by EPD on 5 December 2023. |
Based on the information provided by the Contractor with confirmation by RSS, surcharge removal and fill up were conducted on the complaint date. Despite the dust mitigation measures had been implemented, Strong Monsoon Signal was hoisted by the Hong Kong Observatory, which could be a potential cause of the dust issue. Nevertheless, the Contractor would enhance the green mesh cover of surcharge slope facing the sea and watering more frequently whenever necessary under dry weather. |
2
|
Environmental complaint related to Contract 3 regarding noise opposite Yu Nga Court during restricted hours on 22 November 2023 was referred by EPD on 5 December 2023. |
Based on the information provided by the Contractor with confirmation by RSS, no construction work was conducted during the complained date and time. However, groundwater seepage was spotted at the pipe jacking pit, which could be a potential noise source. Although the complaint case was rectified to prevent recurrence, the Contractor would ensure all works conducted during restricted hours are under a valid CNP and strictly adhere to the conditions in the CNP. |
3
|
Environmental complaint related to Contract 3 regarding noise near Century Link during restricted hours on 26 November 2023 was referred by EPD on 5 December 2023. |
Based on the information provided by the Contractor with confirmation by RSS, no construction work was conducted during the complaint date and time. Nevertheless, the Contractor would convey the complaint case to frontline workers and reminded them to follow the CNP during restricted hours. |
Statistics on complaints,
notifications of summons, successful prosecutions are summarised
in Annex I.
Works to be undertaken in the next monitoring period of
January 2024 are summarized in Table 3.1 below, together with the key
issues and the key mitigation measures:
Table 3.1 Major Activities
for the Next Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
· Placing of sorted public fill · Box culvert construction |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· Construction of pumping station at Portion 6 · Construction of service reservoir, deflector wall and rigid barrier at Portion 3 · CLP cable duct laying works at Wong Lung Hang at Portion 3 · Watermain laying works at Portion 3 along Chung Yan Road, Man Tung Road, Yi Tung Road and inside WSD facilities · Pipe jacking works at Portion 3 · Road widening and watermain laying works at Yi Tung Road at Portion 4 · Installation of ELS and Pipe laying for drainage works at Portion 5A |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation and backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation and pipe laying for rising main and watermain at Portion 146-5 to 146-14 · Pile cap excavation and RC for Pak Mong bridge at 146-3 · Existing seawall demolition at Pak Mong Channel · Trench excavation, pipe piles and pipe laying works at Portions 32 (Sham Shui Kok Drive), Portion 34 Phase 2, and Portions 38 · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot) · Trench excavation at Portion 33 · ELS at Portion 33 Jacking pit · Drilling TAM pipes and grout curtain at Portion 32 for Receiving pit · RC construction of retaining walls FR1 · RC works for Pak Mong Subway Extension Phase 1 · Pipe piles and ELS at Casting Yard A1 and A2 · Bored piles at A1b and A2a · RC works for RW-R2, RW-R3 and ELS for RW-RW4 at Portion 146-2 and 146-6 · RC construction at RW-R7 · Mini-piles at Wall E · GI works for open space at portions 146 · Site clearance and tidiness |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The ET will keep track on the construction works to confirm compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures. The ET will also recommend to the Contractors about
the environmental toolbox topics on the abovementioned key issues for the next
reporting period.
The monitoring results for air
quality monitoring (1-hour TSP) complied with the Action/ Limit levels in the
reporting period. No Action/Limit Level exceedance was recorded for
construction noise monitoring in the reporting period.
Cumulative statistics on
exceedances is provided in Annex
L.
The tentative schedules for environmental monitoring in
January 2024 are provided in Annex
M.
This EM&A Report presents the
findings of the EM&A activities undertaken for the TCE Project during the
period from 1 to 31 December 2023 in accordance with the Updated EM&A
Manual and the requirements of the Environmental Permit (EP-519/2016).
Air quality (1-hour TSP), noise, eco-shoreline,
compensation woodland, in-situ preserved plant species of conservation
importance, transplanted plant species of conservation importance and
post-construction soft shore ecological monitoring were carried out in the
reporting period.
The monitoring results for air
quality monitoring (1-hour TSP) complied with the Action/ Limit levels in the
reporting period.
No exceedance of Action/ Limit
Level was recorded for construction noise monitoring in the reporting
period.
Water quality monitoring was
suspended in the reporting period.
Mangrove eco-shoreline, rocky
eco-shoreline and vertical eco-shoreline were completed. Dry season
monitoring was conducted during the reporting period.
Based on the monitoring results
for post-construction soft shore ecological monitoring, there was no evidence
showing any significant change in intertidal communities when compared against
the data obtained during baseline monitoring. The ET will continue to
observe the change in density or the distribution pattern of horseshoe crab,
seagrass and intertidal soft shore communities taking into
account natural fluctuation in respect of the occurrence and
distribution pattern.
Post-planting monitoring of the
compensation woodland was carried out in the last reporting month.
Monitoring of the in-situ
preserved plant species of conservation importance and monitoring of the
transplanted plant species of conservation importance were carried out in the
reporting period.
Environmental site inspections
were carried out during the reporting period. Recommendations on remedial
actions were given to the Contractors for the deficiencies identified during
the site inspections.
There were
no notification of summons or prosecution recorded in the reporting
period. One (1) environmental complaint related to Contract 1 and two (2)
environmental complaints related to Contract 3. Investigations were
conducted for the environmental complaint in
accordance with the complaint handling process as stated in the Complaint
Management Plan.
The ET will keep track on the construction works to confirm compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures.
|
|
|
|
[1]
ERM (2018a). Updated Environmental Monitoring and Audit Manual for Tung
Chung New Town Extension. Deposited to EPD under EP-519/2016
[2]
Arup (2015). Environmental Impact Assessment Report for Tung Chung New
Town Extension. Deposited to EPD under Register No. AEIAR-196/2016
[3]
Impact monitoring at monitoring station NMS-CA-1A commenced on 19 September
2018 in view of the close vicinity of the construction works near the
residential area at Century Link.
[4]
Due to land handover issue, NMS-CA-1A was relocated to Ying Hong Road which is
located 60m away from the original location. Proposal on the relocation
of NMS-CA-1A was approved by IEC on 23 November 2018. Noise monitoring at
the relocated location commenced since 24 November 2018.
[5]
ERM (2018b). Baseline Monitoring Report for Tung Chung New Town Extension
(East). Submitted to EPD under EP-519/2016